The Regional Municipality of York (York Region) needed to replace a culvert located on Major Mackenzie Drive West in the City of Vaughan, Ontario. The original culvert, which carries the West Don River under Major Mackenzie Drive, was about 50 years old and made of steel pipe. Major Mackenzie Drive had to be fully closed in order to safely and effectively complete the work to replace the older culvert with the new one. This had to be done over a period of two months to comply with restrictions with respect to environmental in-water work timing.
During the consultation period, the City of Vaughan requested that the project include additional pieces of City Infrastructure, which included another culvert. This second culvert would be used to create a passage under Major Mackenzie Drive for both pedestrians and cyclists and would eventually be linked to the new proposed trail system.
Precast concrete was selected for this replacement project because it offers the following benefits:
York Region contacted various precast concrete producers to receive input on the design and manufacturing of the culverts needed for the project and to ensure the structural integrity and minimize any potentials issues during the production phase. The culvert components also had to be ready as soon as the older culvert was exposed and ready for replacement.
In the spring of 2019, the precast concrete manufacturer, DECAST, was awarded the contract to design, produce and deliver the culvert units for the replacement project. The schedule to deliver the culverts components was incredibly tight. Both culverts had to be manufactured by the end of June 2019 to meet the aggressive eight-week construction schedule. It was imperative that the culverts were delivered on time because any delays could have resulted in longer road closures and potential significant financial implications. The design of the culverts was completed in consultation with York Region and the precast concrete manufacturer was able to meet the project timelines.
The precast concrete producer was also responsible for the delivery of the products to the construction site which was crucial in respecting the tight project schedule. The components were delivered overnight to reduce impacts to local traffic especially during rush hour. The experienced and highly knowledgeable team at DECAST shipped all 53 precast concrete pieces for the two large culverts in only five days. Major Mackenzie Drive was only closed for eight weeks from June 17, 2019 to August 12, 2019.
Project Details
The West Don River Culvert:
The Pedestrian/Cycling Underpass:
In just eight weeks, the team accomplished the following:
Photos 1, 2 and 4 courtesy of York Region. Photo 3 from CCPPA Concrete Pipe Journal (Summer issue).
Source: CCPPA- https://ccppa.ca/major-mackenzie-drive-culvert-replacement/ Article by: Jackson Marin, P.Eng. Project Manager, Capital Planning and Delivery, Transportation Services – York Region.
View our latest issue of the popular Imagineering Magazine.